New expressway may cost up to $5b

By Christopher Tan, Senior Correspondent

THE new Marina Coastal Expressway (MCE), which will link the new downtown to the western and north-eastern suburbs, is busting its budget in a big way.

With four out of six major contracts awarded, expenditure on the 5km-long underground and undersea road has already hit $3.1 billion - $600 million more than its $2.5 billion estimated price tag.

When the five-lane dual-carriageway expressway opens in 2013, it could cost between $4 billion and $5 billion, which will make it the costliest road here for years to come.

The Land Transport Authority (LTA) has attributed the cost overrun to a general spike in construction cost, and also to poor soil conditions that required strong temporary walls to prevent accidents.

A former LTA executive said: "The cost is staggering. Compared with it, the KPE is nothing."

The 12km-long, largely underground Kallang-Paya Lebar Expressway (KPE) cost $142 million per km, nearly four times the $37.5 million spent on the Central Expressway in 1991.

Another expensive road to come is the 21km-long, $8 billion North-South Expressway to link Thomson to the city. To be completed in 2020, it is now expected to cost $381 million per km. But should the MCE hit $5 billion, it would top them all, costing an unprecedented $1 billion per km.

The project is so massive that civil works have to be carved up into six portions, so that the builders are not overstretched.

Even so, industry players said each portion would pose a cash-flow challenge to builders. The civil contracts have so far been secured by Ssangyong Engineering & Construction, Samsung C&T, Penta-Ocean Construction and Sato Kogyo-Daelim Industrial ? all foreign groups.

Elaborating on the cost spiral, LTA chief executive Yam Ah Mee said construction costs had gone up.

"Given the poor soil conditions and the reclaimed land at the location where the MCE will run and the many engineering challenges, it is important that we put in place a more comprehensive and robust temporary wall system for the tunnel excavations."

Construction industry observers said such beefed-up engineering requirements - mandatory since the Nicoll Highway collapse in 2004 - contribute to the higher costs.

The LTA declined to reveal the revised cost of the project, saying that doing so could influence bids for the remaining contracts.

The MCE joins the newly opened KPE to the Ayer Rajah Expressway. It links the new Marina South financial centre to the rest of Singapore.

This article was first published in The Straits Times on Nov 4, 2008.


For more The Straits Times stories, click here.


 

 
STORY INDEX
 
  GM to announce 'important changes' with Q3 results
   
 
  Infiniti offers 0% financing on 2008 models
   
 
  Fill her up please, and make it myco-diesel
   
 
  Toyota halves profit forecast after first-half slump
   
 
  US approves loan rules, auto execs lobby for more
   
 
  Vietnam says they need funds for 5,900 km of expressways
   
 
  GM says auto industry faces 'critical' 100 days
   
 
  Toyota yr operating profit sees a 8-yr low
   
 
  New expressway may cost up to $5b
   
 
  Overseas ERP going green
   
>> RELATED STORY
New expressway may cost up to $5b
Electric cars, buses among ideas to energise Singapore
Fewer cabbies flout taxi-stand rule
No parking? Fine
129 cases of vehicles hitting road structures

Elsewhere in AsiaOne...

Investor Relations: Full-year profit for 79 companies up 29%

News: S'pore, Kuwait ink open skies agreement

Wine,Dine&Unwind: Smith Street Food Complex reopens after two years

Travel: Go on, take a staycation

Health: The art of eight limbs

Digital: Leading 3D software provider picks S'pore as regional HQ

Business: Singapore firms ahead in keeping foreign talent on local terms: PwC

Just Women: Jacqueline Law has hush-hush wedding

Multimedia: Better local searches

 

We welcome contributions, comments and tips.
a1motor@sph.com.sg