The current Electronic Road Pricing (ERP) gantry at Bendemeer Road will be relocated 100m further down the road on Nov 24.

The installation of the new gantry is expected to be completed in Dec 2008.

Motorists will see two separate ERP gantries along Bendemeer Road when the new gantry is being installed. However, the new ERP gantry will not be operational until the existing gantry is decommissioned.

During this period, motorists joining Bendemeer Road from the slip road off PIE (Tuas) will pass through two ERP gantries - the existing ERP gantry along the slip road off PIE (Tuas) and the relocated ERP gantry along Bendemeer Road.

The existing ERP gantry along the slip road off PIE (Tuas) will not be operational during this period. Motorists will only be charged when they pass the relocated ERP gantry along Bendemeer Road.

The switch over of the ERP gantries along Bendemeer Road will be carried out in early Feb 2009.

The relocated ERP gantry will have the same ERP rates and operating hours as the current Bendemeer Road ERP gantry.

Information signboards will be displayed at key approaches leading to the Bendemeer Road gantry to inform motorists of the relocation of the gantry.

The relocation is to facilitate the construction of the road tunnel as part of the Woodsville Interchange upgrading.

The relocated ERP gantry will be shifted back to its current location when construction works are completed, which is by end 2011.

 